How to Define a Project

Project definition is the process of documenting key parameters for a project. A good project definition document answers the following questions:

Kinds of Project Definition Documents

Different organizations use different names for their definition documents. Some of the more common names are:

The Anatomy of a Definition Document

“The most important and difficult part of the project is its beginning….  If done carefully, the project has a chance of success.  If done carelessly, or not at all, the project is doomed to failure. ”

–Wysocki, Beck and Crane

In order to properly define the project, the project manager must meet with the key sponsor and stakeholders to get consensus on what the definition is.  You would ideally complete this step before setting the budget and schedule, but it may be necessary to redefine some terms post-approval. To answer the questions above, the document will usually consist of the following sections:

Defining What “Done” Means

The last bullet above is important for avoiding scope creep. The definition process is the project manager’s first and most critical opportunity to limit the project scope. The best way to do so is clearly articulating completion criteria for the major project deliverables and for the overall project.

A solid completion statement will tie the deliverables and their acceptance together in a logical way.

A project completion statement might look like the following:

The design task will be complete when the project manager provides the Design Report, as outlined in the deliverables guideline section, and it is accepted by the project sponsor according to the acceptance procedure in Appendix C.

Statements like this should appear in both the completion criteria section of the definition document and the approach section. This will ensure there are no doubts as to exactly what “done” means.

The most difficult part of writing a definition document is setting limits. You need to define up front what the project does include, as well as what it does not include.

For example, a project charter might say, “The goal of this project is to network all facilities in Maryland.” This would leave the project manager vulnerable to a response of, “While you’re at it, why don’t you include the facilities in Virginia?” On the other hand, a project charter that says, “The goal of this project is to network all facilities in Maryland.  Facilities in Virginia will be networked in a separate project during the next fiscal year,” provides some defense when people ask for out-of-scope modifications.

Backing into Project End Dates

Project managers are often assigned to a project after the project finish date, budget, and resources have been defined.  If an SME doesn’t have a role in the initial definition of these important parameters, a work plan and schedule may not exist yet.  The only way to achieve any degree of certainty in these figures is to lay out a schedule that demonstrates whether or not there is enough money, the right number and kind of people, and enough time to produce the deliverables.

Project managers affectionately call this process backing into the schedule. The painfulness of this process highlights the importance of involving the project manager early in the definition of a project.

Some project managers wonder, How do you handle projects without defined end dates. In fact, most project managers would prefer to build the plan before they commit to any kind of project completion date.

For more help on navigating the challenges of project management, contact our experts today.

Recent Insights

January 3, 2025

How AI Can Unlock the Final Frontier of Project Management

Most opportunities for digital disruption have happened when there is wasted capacity because of a disconnect with demand. How many empty houses were there before AirBnB connected people leaving town with people who wanted...